Columbus Park Public Restroom Building and Pavilion Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct the public restroom building and pavilion in Columbus Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2022
Projected Completion Date:
April 2024
Adjusted Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Columbus Park, Manhattan
between Baxter Street and Mulberry Street
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024