Shore Park and Parkway Vinland Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Vinland Playground at Shore Park and Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: October 2022
Completion Date: May 2023

Construction

Start Date: September 2023
Projected Completion Date: September 2024
Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $3,400,000
Funding Source: City Council

Location

Shore Park and Parkway, Brooklyn
94th Street & Ridge Boulevard
Community Board: 10

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024