Ocean Parkway Sitting Areas Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct two sitting areas along Ocean Parkway at East 8th Street and at Sherman Street with new pavement, benches and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2020
Projected Completion Date:
February 2021
Completion Date:
March 2021
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Completion
Date:
January 2023
Construction
Start Date: April 2023
Projected Completion Date:
April 2024
Completion Date: April 2024
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Locations
-
Park, Brooklyn
Northside Ocean Parkway & Sherman Street
Community Board: 07 -
Park, Brooklyn
Southside Ocean Parkway & East 8th Street
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024