Ocean Parkway Sitting Areas Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct two sitting areas along Ocean Parkway at East 8th Street and at Sherman Street with new pavement, benches and plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2020
Projected Completion Date: February 2021
Completion Date: March 2021

Procurement

Start Date: March 2021
Projected Completion Date: December 2021
Completion Date: January 2023

Construction

Start Date: April 2023
Projected Completion Date: April 2024
Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: $720,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • Park, Brooklyn
    Northside Ocean Parkway & Sherman Street
    Community Board: 07
  • Park, Brooklyn
    Southside Ocean Parkway & East 8th Street
    Community Board: 07
 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024