Marine Park Oval Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the inner and outer walking paths of the oval as well as several connecting paths at Marine Park, including new asphalt pavement, bottle fillers and benches.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: April 2023

Construction

Start Date: June 2023
Projected Completion Date: September 2024
Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $10,499,000
Funding Sources:
  • City Council
  • Mayoral

Location

Marine Park, Brooklyn
Avenue U, Stuart Street, Fillmore Avenue, East 33rd Street
Community Board: 15, 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024