John J. Carty Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground at John J. Carty Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
November 2021
Procurement
Start Date: November 2021
Projected Completion Date:
August 2022
Completion
Date:
April 2023
Construction
Start Date: May 2023
Projected Completion Date:
April 2024
Completion Date: January 2024
Understand how we build parks.
Funding
Funding Source: City Council
Location
John J Carty Park, Brooklyn
Fort Hamilton Parkway between 94th Street and 101st Street
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025