John J. Carty Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground at John J. Carty Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: November 2021

Procurement

Start Date: November 2021
Projected Completion Date: August 2022
Completion Date: April 2023

Construction

Start Date: May 2023
Projected Completion Date: April 2024
Completion Date: January 2024

Understand how we build parks.

Funding

Total Funding: $4,212,000
Funding Source: City Council

Location

John J Carty Park, Brooklyn
Fort Hamilton Parkway between 94th Street and 101st Street
Community Board: 10

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project