Daniel O'Connell Playground Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct Daniel O'Connell Playground.

Project Notes

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: June 2024

Procurement

Start Date: June 2024
Projected Completion Date: February 2026

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • City Council
  • Mayoral

Location

Daniel M. O'Connell Playground, Queens
196th Street, Murdock Avenue, 197th Street, 113th Avenue
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 03/28/2025