Laurelton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    33% complete

This project will reconstruct Laurelton Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: January 2022
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: February 2023
Completion Date: January 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $4,000,000
Funding Source: City Council

Location

Laurelton Playground, Queens
Brookville Blvd between 136th and 138th Avenues
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower