Nameoke Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a public restroom building at Nameoke Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: April 2024

Construction

Start Date: September 2024
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $3,692,000
Funding Source: Mayoral

Location

Nameoke Park, Queens
Nameoke Avenue, Augustina Avenue
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024