Nameoke Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will construct a public restroom building at Nameoke Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: April 2024

Construction

Start Date: October 2024
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $3,692,000
Funding Source: Mayoral

Location

Nameoke Park, Queens
Nameoke Avenue, Augustina Avenue
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025