Nameoke Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
6% complete
This project will construct a public restroom building at Nameoke Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
December 2021
Procurement
Start Date: December 2021
Projected Completion Date:
September 2022
Completion
Date:
April 2024
Construction
Start Date: October 2024
Projected Completion Date:
March 2026