Brookville Park Baseball Fields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    12% complete

This project will reconstruct two natural turf baseball fields in Brookville Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2020
Projected Completion Date: May 2022
Completion Date: May 2023

Procurement

Start Date: May 2023
Projected Completion Date: May 2024
Completion Date: October 2024

Construction

Start Date: October 2024
Projected Completion Date: October 2025

Understand how we build parks.

Funding

Total Funding: $5,700,000
Funding Sources:
  • Borough President
  • City Council

Location

Brookville Park, Queens
232nd Street and 147th Avenue
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025