Brookville Park Baseball Fields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct two natural turf baseball fields in Brookville Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2020
Projected Completion Date: May 2022
Completion Date: May 2023

Procurement

Start Date: May 2023
Projected Completion Date: May 2024
Completion Date: October 2024

Construction

Start Date: October 2024
Projected Completion Date: October 2025

Understand how we build parks.

Funding

Total Funding: $5,700,000
Funding Sources:
  • Borough President
  • City Council

Location

Brookville Park, Queens
232nd Street and 147th Avenue
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project