Hallets Cove Playground Handball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the handball courts at Hallets Cove Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2020
Projected Completion Date: November 2020
Completion Date: September 2020

Procurement

Start Date: September 2020
Projected Completion Date: May 2021
Completion Date: May 2023

Construction

Start Date: May 2023
Projected Completion Date: November 2023
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $450,000
Funding Source: Borough President

Location

Hallets Cove Playground, Queens
Along East River, 1st Street, Astoria Blvd, and Vernon Blvd.
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024