Frederick B. Judge Playground Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct Frederick B. Judge Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
June 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Frederick B. Judge Playground, Queens
111th Avenue, Linden Boulevard, 134th Street, 135th Street
Community Board: 10
Project Staff
Project Liaison: Meira Berkower