Cunningham Park 210th Street Playground Reconstruction
-
100% complete
-
100% complete
-
98% complete
This project will reconstruct 210th Street Playground at Cunningham Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2019
Projected Completion Date:
December 2020
Completion Date:
January 2021
Procurement
Start Date: January 2021
Projected Completion Date:
October 2021
Completion
Date:
July 2023
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Cunningham Park, Queens
210th Street and 73rd Avenue
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024