Nameoke Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct Nameoke Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
October 2020
Procurement
Start Date: October 2020
Projected Completion Date:
July 2021
Completion
Date:
June 2022
Construction
Start Date: August 2022
Projected Completion Date:
August 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Nameoke Park, Queens
Nameoke Avenue and Augustina Avenue
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025