Sohncke Square Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Sohncke Square.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
March 2021
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Completion
Date:
December 2022
Construction
Start Date: July 2023
Projected Completion Date:
July 2024
Completion Date: July 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Sohncke Square, Queens
Woodside Avenue, Roosevelt Avenue, 58th Street
Community Board: 02
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025