Joe Michael's Mile Waterfront Structural Reconstruction (Hurricane Sandy)

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the waterfront Parks infrastructure damaged by Hurricane Sandy at Joe Michael's Mile.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2022
Adjusted Completion Date: January 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Cross Island Parkway, Queens
Cross Island Parkway between Totten Avenue and 28th Avenue
Community Board: 07, 11, 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024