Manhattan Street Tree Planting FY21 - Community Boards 3, 6
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 3 and 6 in Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
November 2019
Completion Date:
March 2021
Procurement
Start Date: March 2021
Projected Completion Date:
November 2021
Completion
Date:
October 2022
Construction
Start Date: November 2022
Projected Completion Date:
November 2024
Completion Date: October 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024