Queens Street Tree Planting FY21 - Community Board 7 (QG-1019M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Board 7 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: January 2022

Construction

Start Date: March 2022
Projected Completion Date: October 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $882,000
Funding Source: Mayoral