Staten Island Street Tree Planting FY21 (RG-619M)
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
November 2019
Completion Date:
September 2019
Procurement
Start Date: September 2019
Projected Completion Date:
June 2020
Completion
Date:
April 2022
Construction
Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date: April 2023
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 11/22/2024