Brooklyn Street Tree Planting FY21 - Community Boards 12, 14 (BG-1619M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 12 and 14 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: August 2021

Construction

Start Date: October 2021
Projected Completion Date: October 2022
Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $2,990,000
Funding Source: Mayoral

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024