Queens Street Tree Planting FY21 - Community Boards 8, 11-13
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 8 and 11-13 in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
November 2019
Completion Date:
September 2019
Procurement
Start Date: September 2019
Projected Completion Date:
May 2020
Completion
Date:
September 2021
Construction
Start Date: October 2021
Projected Completion Date:
October 2024
Completion Date: October 2024
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- Private
Last updated: 11/22/2024