Manhattan Street Tree Planting FY21 - Community Boards 1, 2, 4, 5, 7-12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will plant new trees in Community Boards 1, 2, 4, 5, and 7-12 in Manhattan.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: April 2021
Completion Date: June 2022

Construction

Start Date: June 2022
Projected Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $13,565,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Various locations in Manhattan

Project Staff