Bronx Street Tree Planting FY21 - Community Boards 5-8, 11, 12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    98% complete

This project will plant new trees in Community Boards 5-8, 11, and 12 in the Bronx.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: May 2020
Completion Date: January 2022

Construction

Start Date: March 2022
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $10,763,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in the Bronx

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024