Van Cortlandt Park Skate Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a skate park in Van Cortlandt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2013
Projected Completion Date: June 2015
Completion Date: August 2015

Procurement

Start Date: August 2015
Projected Completion Date: May 2016
Completion Date: April 2019

Construction

Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $1,001,000
Funding Sources:
  • City Council
  • Mayoral

Location

Van Cortlandt Park, Bronx
Broadway and Van Cortlandt Park South
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025