Flushing Meadows Corona Park Queens Storehouse Reconstruction
-
100% complete
-
100% complete
-
47% complete
This project will reconstruct the Queens Storehouse in Flushing Meadows Corona Park. The work will include reconstructing portions of the roof, exterior walls, and floor slab; new screening, signage, and a staging yard; and improved drainage and landscape restoration.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2020
Projected Completion Date:
May 2021
Completion Date:
March 2022
Procurement
Start Date: March 2022
Projected Completion Date:
December 2022
Completion
Date:
February 2024
Construction
Start Date: May 2024
Projected Completion Date:
November 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
43 Meridian Road
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025