Bronx and Queens Reforestation FY20

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    17% complete

This project will remove invasive species and plant new and replacement trees in the Bronx and Queens.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: August 2019
Completion Date: April 2023

Procurement

Start Date: April 2023
Projected Completion Date: June 2021
Completion Date: June 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2027

Understand how we build parks.

Funding

Total Funding: $1,170,000
Funding Sources:
  • City Council
  • Mayoral

Location

Various locations in the Bronx and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025