Manhattan Reforestation FY20

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    30% complete

This project will remove invasive species and plant new and replacement trees in Manhattan.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: August 2019
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: April 2023

Construction

Start Date: October 2023
Projected Completion Date: September 2026

Understand how we build parks.

Funding

Total Funding: $1,035,000
Funding Source: Mayoral

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024