Riverside Park Cherry Walk Greenway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct portions of the Cherry Walk greenway in Riverside Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2022
Projected Completion Date: July 2022
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Completion Date: March 2024

Construction

Start Date: September 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Source: Mayoral

Location

Riverside Park, Manhattan
West 100th Street to St. Clair Place between the Hudson River and Henry Hudson Parkway
Community Board: 07, 09

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025