Riverside Park Cherry Walk Greenway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct portions of the Cherry Walk greenway in Riverside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2022
Projected Completion Date: July 2022
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Completion Date: March 2024

Construction

Start Date: September 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Source: Mayoral

Location

Riverside Park, Manhattan
West 100th Street to St. Clair Place between the Hudson River and Henry Hudson Parkway
Community Board: 07, 09

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024