Jackie Robinson Recreation Center HVAC System Reconstruction
-
100% complete
-
100% complete
-
40% complete
This project will reconstruct the HVAC system at Jackie Robinson Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2019
Projected Completion Date:
October 2020
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
October 2022
Construction
Start Date: October 2023
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jackie Robinson Park, Manhattan
85 Bradhurst Avenue
Community Board: 09, 10
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024