Jackie Robinson Recreation Center HVAC System Reconstruction
-
100% complete
-
100% complete
-
40% complete
This project will reconstruct the HVAC system at Jackie Robinson Recreation Center.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2019
Projected Completion Date:
October 2020
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
October 2022
Construction
Start Date: October 2023
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jackie Robinson Park, Manhattan
85 Bradhurst Avenue
Community Board: 09, 10
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025