Rev. T. Wendell Foster Park Skate and Bike Park Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct the skate and bike park at Rev. T. Wendell Foster Park.
Project Notes
Project Update: Parks is continuing to develop the documents to build this project.
Project Timeline
Design
Assigned & Start Date: December 2023
Projected Completion Date:
May 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
- State
Location
Rev. T. Wendell Foster Park and Recreation Center , Bronx
River Avenue and East 164th Street
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024