Bellerose Playground Reading Garden Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a reading garden at Bellerose Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: January 2021

Procurement

Start Date: January 2021
Projected Completion Date: October 2021
Completion Date: April 2023

Construction

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: $362,000
Funding Sources:
  • Mayoral
  • State

Location

Bellerose Playground, Queens
85th Avenue between 248th Street and 249th Street
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024