Lopez Playground Modular Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a modular public restroom building at Lopez Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: June 2021

Procurement

Start Date: June 2021
Projected Completion Date: February 2022
Completion Date: June 2022

Construction

Start Date: September 2022
Projected Completion Date: December 2023
Completion Date: March 2024

Understand how we build parks.

Funding

Total Funding: $3,865,000
Funding Source: Mayoral

Location

Lopez Playground, Staten Island
Palma Drive between Targee Street and Oder Avenue
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024