Citywide Olympic Pool Mechanical Systems Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the mechanical systems at various Olympic pools citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2019
Projected Completion Date:
January 2020
Completion Date:
October 2021
Procurement
Start Date: October 2021
Projected Completion Date:
October 2020
Completion
Date:
July 2023
Construction
Start Date: October 2023
Projected Completion Date:
September 2024
Completion Date: January 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Betsy Head Park, Brooklyn
Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
Community Board: 16 -
Highbridge Park, Manhattan
West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues
Community Board: 10, 12 -
Jackie Robinson Park, Manhattan
85 Bradhurst Avenue
Community Board: 09, 10 -
Lyons Pool, Staten Island
Murray Hulbert Avenue between Victory Boulevard and Hannah Street
Community Board: 01
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024