Citywide Olympic Pool Mechanical Systems Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the mechanical systems at various Olympic pools citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2019
Projected Completion Date: January 2020
Completion Date: October 2021

Procurement

Start Date: October 2021
Projected Completion Date: October 2020
Completion Date: July 2023

Construction

Start Date: October 2023
Projected Completion Date: September 2024
Completion Date: January 2024

Understand how we build parks.

Funding

Total Funding: $535,000
Funding Source: Mayoral

Locations

  • Betsy Head Park, Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
    Community Board: 16
  • Highbridge Park, Manhattan
    West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues
    Community Board: 10, 12
  • Jackie Robinson Park, Manhattan
    85 Bradhurst Avenue
    Community Board: 09, 10
  • Lyons Pool, Staten Island
    Murray Hulbert Avenue between Victory Boulevard and Hannah Street
    Community Board: 01
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024