Ranaqua Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof at Ranaqua in Bronx Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: September 2020
Completion Date: November 2020

Procurement

Start Date: November 2020
Projected Completion Date: July 2021
Completion Date: June 2022

Construction

Start Date: August 2022
Projected Completion Date: February 2024
Completion Date: February 2024

Understand how we build parks.

Funding

Total Funding: $4,347,000
Funding Source: Mayoral

Location

Bronx Park, Bronx
Birchall Avenue near Bronx River Parkway
Community Board: 06, 07, 11, 12

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025