Brooklyn and Staten Island Emerald Ash Borer (EAB) Related Tree Removal
-
100% complete
-
100% complete
-
100% complete
This project will remove trees with emerald ash borer (EAB) in Brooklyn and Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
April 2019
Completion Date:
April 2019
Procurement
Start Date: April 2019
Projected Completion Date:
December 2019
Completion
Date:
December 2020
Construction
Start Date: April 2021
Projected Completion Date:
March 2023
Completion Date: March 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations in Brooklyn and Staten Island
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024