Monsignor Kett Playground Public Restroom Building Construction
-
100% complete
-
100% complete
-
52% complete
This project will construct a public restroom building in Monsignor Kett Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date:
August 2020
Procurement
Start Date: August 2020
Projected Completion Date:
May 2021
Completion
Date:
June 2023
Construction
Start Date: September 2023
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Monsignor Kett Playground, Manhattan
West 204th Street between 10th Avenue and Nagle Avenue
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024