Monsignor Kett Playground Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    52% complete

This project will construct a public restroom building in Monsignor Kett Playground.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021
Completion Date: June 2023

Construction

Start Date: September 2023
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $5,126,000
Funding Source: Mayoral

Location

Monsignor Kett Playground, Manhattan
West 204th Street between 10th Avenue and Nagle Avenue
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024