Sheltering Arms Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
99% complete
This project will reconstruct the public restroom building in Sheltering Arms Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
March 2020
Procurement
Start Date: March 2020
Projected Completion Date:
December 2020
Completion
Date:
January 2022
Construction
Start Date: March 2022
Projected Completion Date:
September 2023
Adjusted Completion Date: September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Sheltering Arms Playground, Manhattan
West 129th Street, Amsterdam Avenue, West 126th Street, Old Broadway
Community Board: 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024