Woodlawn Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the public restroom building in Woodlawn Playground in Van Cortlandt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date:
May 2020
Procurement
Start Date: May 2020
Projected Completion Date:
February 2021
Completion
Date:
March 2024
Construction
Start Date: March 2025
Projected Completion Date:
September 2026
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Van Cortlandt Park, Bronx
Van Cortlandt Park East between Oneida Avenue and Kepler Avenue
Community Board: 07, 08, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024