Commodore Barry Park Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Commodore Barry Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: February 2021
Completion Date: January 2022

Construction

Start Date: May 2022
Projected Completion Date: October 2023
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $3,574,000
Funding Source: Mayoral

Location

Commodore Barry Park, Brooklyn
Flushing Avenue, North Elliot Place, Park Avenue and Navy Street
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025