Commodore Barry Park Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Commodore Barry Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2019
Projected Completion Date:
April 2020
Completion Date:
May 2020
Procurement
Start Date: May 2020
Projected Completion Date:
February 2021
Completion
Date:
January 2022
Construction
Start Date: May 2022
Projected Completion Date:
October 2023
Completion Date: October 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Commodore Barry Park, Brooklyn
Flushing Avenue, North Elliot Place, Park Avenue and Navy Street
Community Board: 02
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project