Icahn Stadium Electrical Service Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the electrical service line from Icahn Stadium transformers to the PEP Academy trailer complex in Randall's Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2018
Projected Completion Date:
February 2019
Completion Date:
March 2019
Procurement
Start Date: March 2019
Projected Completion Date:
December 2019
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
October 2021
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Randall's Island Park, Manhattan
Icahn Stadium to the PEP Academy trailer complex
Community Board: 11
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025