East River Esplanade Stabilization and Reconstruction Phase 3

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will stabilize and reconstruct portions of the East River Esplanade.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2019
Projected Completion Date: July 2020
Completion Date: October 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024