East River Esplanade Stabilization and Reconstruction Phase 3
-
100% complete
-
0% complete
-
0% complete
This project will stabilize and reconstruct portions of the East River Esplanade.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
July 2020
Completion Date:
October 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Locations
-
Andrew Haswell Green Park, Manhattan
FDR, East River, East 59 & East 63 Streets
Community Board: 08 -
East River Esplanade, Manhattan
FDR Drive, East 90 to East 125 Streets
Community Board: 08, 11 -
East River Walk, Manhattan
FDR Drive, East 63 to East 81 Streets
Community Board: 08
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024