Pelham Bay Park Seawall Reconstruction (Hurricane Sandy)
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct the waterfront Parks infrastructure damaged by Hurricane Sandy at Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
January 2022
Adjusted Completion Date:
November 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Pelham Bay Park, Bronx
Watt Avenue & Middletown Road
Community Board: 10, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project