Citywide Synthetic Turf Field Reconstruction (CNYG-1119MA)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct synthetic turf fields citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2018
Projected Completion Date:
March 2019
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Completion
Date:
December 2022
Construction
Start Date: March 2023
Projected Completion Date:
March 2025
Completion Date: September 2024
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- Private
Location
Various locations citywide
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024