Asser Levy Recreation Center HVAC System Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the HVAC system at Asser Levy Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2019
Projected Completion Date: March 2021
Completion Date: November 2022

Procurement

Start Date: November 2022
Projected Completion Date: August 2023
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council
  • Federal
  • Mayoral

Location

Asser Levy Playground, Manhattan
Asser Levy Place between East 23rd Street and East 25th Street
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024