Havemeyer Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Havemeyer Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
May 2022
Construction
Start Date: July 2022
Projected Completion Date:
January 2024
Completion Date: January 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Havemeyer Playground, Bronx
Watson Avenue between Havemeyer Avenue and East 177th Street
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 02/21/2025