Captain Tilly Park Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Captain Tilly Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: January 2022

Construction

Start Date: September 2022
Projected Completion Date: March 2024
Completion Date: June 2024

Understand how we build parks.

Funding

Total Funding: $2,122,000
Funding Source: Mayoral

Location

Captain Tilly Park, Queens
Highland Avenue between 165th Street and 166th Street
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024