East River Esplanade East 36th-38th Streets Seawall Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the seawall and waterfront infrastructure at the East River Esplanade .

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: October 2021
Completion Date: June 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

East River Esplanade, Manhattan
FDR Drive between East 36th and East 38th Streets
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025