East River Esplanade East 36th-38th Streets Seawall Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the seawall and waterfront infrastructure at the East River Esplanade .
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2019
Projected Completion Date:
October 2021
Completion Date:
June 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
East River Esplanade, Manhattan
FDR Drive between East 36th and East 38th Streets
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024