East River Esplanade Stabilization and Reconstruction Phase 2

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will stabilize and reconstruct portions of the East River Esplanade.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2019
Projected Completion Date: March 2020
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Adjusted Completion Date: April 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

East River Esplanade, Manhattan
East River Esplanade between East 96th Street and East 125th Street
Community Board: 08, 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024