East River Esplanade Stabilization and Reconstruction Phase 2
-
100% complete
-
60% complete
-
0% complete
This project will stabilize and reconstruct portions of the East River Esplanade.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
March 2020
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Adjusted Completion
Date:
April 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
East River Esplanade, Manhattan
East River Esplanade between East 96th Street and East 125th Street
Community Board: 08, 11