Highland Park Lower East Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the eastern half of the lower playground area, and performance area at Highland Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
February 2020
Completion
Date:
June 2021
Construction
Start Date: June 2021
Projected Completion Date:
June 2022
Completion Date: February 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highland Park, Queens
Jamaica Avenue between Lynwood and Elton Streets
Community Board: 05, 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025