Queens Community Boards 8-14 and Bronx Reforestation FY20

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new and replacement trees in the Bronx, and in Queens Community Boards 8-14.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: April 2021

Construction

Start Date: June 2021
Projected Completion Date: December 2023
Completion Date: November 2023

Understand how we build parks.

Funding

Total Funding: $1,133,000
Funding Source: Mayoral

Location

Various locations in the Bronx and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024