Queens Community Boards 1-7 and Brooklyn Reforestation FY20

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new and replacement trees in Brooklyn, and Queens Community Boards 1-7.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: November 2020

Construction

Start Date: January 2021
Projected Completion Date: July 2023
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $1,065,000
Funding Source: Mayoral

Location

Various locations in Brooklyn and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025