Queens Community Boards 1-7 and Brooklyn Reforestation FY20
-
100% complete
-
100% complete
-
100% complete
This project will remove invasive species and plant new and replacement trees in Brooklyn, and Queens Community Boards 1-7.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
February 2019
Completion Date:
March 2019
Procurement
Start Date: March 2019
Projected Completion Date:
December 2019
Completion
Date:
November 2020
Construction
Start Date: January 2021
Projected Completion Date:
July 2023
Completion Date: December 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations in Brooklyn and Queens
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025